Nuru, Melania Ariani Putri (2020) ANALYSIS OF FACTORS CAUSING DELAY IN THE IMPLEMENTATION OF BUILDING CONSTRUCTION PROJECTS IN NGADA REGENCY. S1 thesis, UNIVERSITAS ATMA JAYA YOGYAKARTA.

Text (Melania Ariani Putri Nuru)
151316282 0.pdf

File Pdf (934kB)
Text
151316282-1.pdf

File Pdf (455kB)
Text
151316282-2.pdf

File Pdf (382kB)
Text
151316282-3.pdf
Restricted to Registered users only

File Pdf (612kB)
Text
151316282-4.pdf
Restricted to Registered users only

File Pdf (558kB)
Text
151316282-5.pdf

File Pdf (1MB)

Abstract

Construction is an activity to build facilities and infrastructure. Although
construction activities are known as one job, but in reality construction is a unit of
activity consisting of several other different jobs. For the successful implementation of
a construction project, effective planning is essential. problems can arise if there is a
mismatch between the plans that have been made and their implementation. So that the
impact that often occurs is the delay in the implementation of the project, which can
also be accompanied by an increase in the cost of implementing the project. Ngada is
one part of the regency in Indonesia which is currently carrying out many construction
projects, In the implementation of this construction project, there are things that are
always a concern, namely the inaccuracy of project completion time according to the
contract value. there needs to be an effort to find out the main causes of the delays in
the construction project itself, in order to find a solution to minimize the delay in the
implementation of construction projects in Ngada Regency.
This research was conducted to determine what factors influence the delay in
the implementation of a building construction project in Ngada Regency and whether
there is harmony among respondents. This research was conducted by distributing
questionnaires to respondents. Respondents gave an assessment of the factors of delay.
The final result of the data analysis is in the form of thevalue mean of the delay
factors contained in the questionnaires that have been distributed. There are 8 factors
of delay including, Material, Labors, Equipment, Financial, Environment, Site
Characteristic, Contract Agreement, Managerial and Scheduling. From the existing
data, it is managed using the SPSS 16.0 program, then the Mean value is obtained.
From the mean value obtained, then sorted according to the largest to the smallest mean
value, where the largest mean value is the most influencing factor, namely managerial
and time factors. Then from processing using SPSS 16.0, the Kendall W value and the
Asymptotic Significance value are also obtained, which indicate harmony between
respondents in Ngada Regency.

Item Type: Thesis (S1)
Uncontrolled Keywords: Construction, Delay Factor, Kendall W Method, SPSS 16.0.
Subjects: Civil Engineering > Construction Management
Divisions: Fakultas Teknik > Teknik Sipil Internasional
Date Deposited: 03 May 2023 13:10
Last Modified: 03 May 2023 13:51
URI: https://repository.uajy.ac.id/id/eprint/28889

Actions (login required)

View Item
View Item