Agusta, Reza Aldo (2020) TANGGUNG JAWAB PENYEDIA JASA ATAS KETERLAMBATAN PENYELESAIAN PEKERJAAN KONSTRUKSI AKIBAT PANDEMI COVID - 19. S1 thesis, Universitas Atma Jaya Yogyakarta.
1705129491.pdf
File Pdf (1MB)
1705129492.pdf
Restricted to Registered users only
File Pdf (797kB)
Abstract
The title of the legal research is responsibility contractor delayed in completing
construction work due to pandemic covid – 19. The whole world including
Indonensia is in the emergency period of the pandemic covid – 19. During the
emergency period of the pandemic covid – 19, the impact was very massive on all
sectors, including the contraction sector. Development must continue amid the
pandemic covid - 19 due to contract demand that have been agreed by the parties.
Many problems arise with this situation on of which is the period of the final
contruction work. The purpose of the research is to investigate the responsibility
contractor delayed in completing construction work due to pandemic covid – 19.
The research was conducted of normative legal research, research that based on
positive legal norms in the form of legislation. The result of the research is
pandemic Covid – 19 can be categorized as a relative Force Majure so Contractor
can temporarily suspend their work so that the Contractor stille continues
responsibilities the completion of construction work, but delayed in fulfiling the
obigation of completing Contuction Contract.
| Item Type: | Thesis (S1) |
|---|---|
| Uncontrolled Keywords: | Responsibility, Contractor, Contraction Work, Pandemic Covid - 19 |
| Subjects: | Ilmu Hukum > Ekonomi Bisnis |
| Divisions: | Fakultas Hukum > Program Studi Ilmu Hukum |
| Date Deposited: | 22 Apr 2021 04:26 |
| Last Modified: | 22 Apr 2021 04:26 |
| URI: | https://repository.uajy.ac.id/id/eprint/23801 |